Estimating Guidance for CGP
September 2010
California Department of Transportation
Division of Design
Office of Storm Water Management
1120 N Street
Sacramento, California
TABLE OF CONTENTS
1. ESTIMATING BEES ITEMS ...............................................................................................................1
1.1. OVERVIEW ...................................................................................................................................1
1.2. CONSTRUCTION SITE MANAGEMENT (BEES ITEM: 074016)...........................................1
1.3. PREPARE WATER POLLUTION CONTROL PROGRAM (BEES ITEM: 074017) ................1
1.4. PREPARE STORM WATER POLLUTION PREVENTION PLAN (BEES ITEM: 074019) ....1
1.5. RAIN EVENT ACTION PLAN (BEES ITEM: 074056) ...............................................................3
1.6. STORM WATER ANNUAL REPORT (BEES ITEM: 074057) ...................................................4
1.7. STORM WATER SAMPLING AND ANALYSIS DAY (BEES ITEM: 074058) ........................ 4
1.8. RECEIVING WATER BIOASSESSMENT (RL 3) (BEES ITEM:_______)................................ 5
1.9. WATER POLLUTION CONTROL MAINTENANCE SHARING (BEES ITEM: 066595) ........5
1.10. ADDITIONAL WATER POLLUTION CONTROL (BEES ITEM: 066596) ............................... 6
1.11. STORMWATER SAMPLING AND ANALYSIS (BEES ITEM: 066597)...................................6
1.12. ALL OTHER SEPARATE ITEM BMPS.......................................................................................7
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
i
TABLE OF CONTENTS
LIST OF TABLES
T
ABLE 1 [PPDG TABLE F-6: CONSTRUCTION SITE WATER POLLUTION CONTROL] ... ERROR! BOOKMARK NOT
DEFINED
.
List of Figures
FIGURE 1-1 FIND CLIMATE DATA USING D8S INTERNAL WEBSITE ....................................................................3
LIST OF ACRONYMS
BEES Basic Engineering Estimating System
BMPs Best Management Practices
CGP Construction General Permit
CSMP Construction Site Monitoring Program
EPA Environmental Protection Agency
Eqn. Equation
NOAA National Oceanic Atmospheric Administration
NPDES National Pollutant Discharge Elimination System
PE Professional Engineer
PPDG Project Planning and Design Guide
RE Resident Engineer
REAP Rain Event Action Plan
RL Risk Level
RQM Routine Quarterly Monitoring
RWQCB Regional Water Quality Control Board
SAP Sampling and Analysis Plan
SSP Standard Special Provisions
SWM Storm Water Monitoring
SWPPP Storm Water Pollution Prevention Plan
WPC Water Pollution Control
WPCP Water Pollution Control Program
WQPT Water Quality Planning Tool
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
ii
SECTIONFOUR Precipitation and other Climate Data
1. ESTIMATING BEES ITEMS
1.1. OVERVIEW
The new Construction General Permit (CGP: Order No. 2009-009-DWQ, NPDES No.
CAS000002) has different, often increased, requirements for stormwater sampling and
reporting than the old NPDES permit. To accommodate the new CGP requirements in
future highway jobs, the following guidance is offered to estimate the various stormwater
pay items including several new items of work.
The CGP takes a risk-based approach based upon sediment discharge and receiving water
risk. The risk level (RL) increases from RL 1 to RL 3 as the potential threat to water
quality increases. Consequently, some contract items apply to all jobs and some only
apply to those with the higher risk levels.
This estimating guidance applies to all projects including the small construction jobs and
those under the CGP.
1.2. CONSTRUCTION SITE MANAGEMENT (BEES ITEM: 074016)
Examine local BEES bid history to estimate costs for Construction Site Management (SSP
07-346). Coordinate cost estimate with Construction.
1.3. PREPARE WATER POLLUTION CONTROL PROGRAM (BEES ITEM:
074017)
Projects with less than one (1) acre of soil disturbance will have Prepare Water Pollution
Control Program (WPCP). Small construction projects, between 1 and 5 acres of soil
disturbance, that qualify for an EPA Erosivity Waiver will also have a WPCP. Use Table
F-6 to estimate the cost of WPCP.
1.4. PREPARE STORM WATER POLLUTION PREVENTION PLAN (BEES
ITEM: 074019)
Use Table F-6 to estimate the cost of preparing the written document describing the
implementation of the project’s water pollution controls. Projects with one (1) acre or
more disturbed soil area will have Prepare Storm Water Pollution Prevention Plan
(SWPPP). Prepare SWPPP includes the cost to prepare the Construction Site Monitoring
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
1
-
--
-
SECTIONFOUR Precipitation and other Climate Data
Program (CSMP) that includes Sampling and Analysis Plan (SAP) and conduct visual
mo
nitoring.
Table F
Table FTable F
Table F 6: Construction Site Water Pollution Control
6: Construction Site Water Pollution Control6: Construction Site Water Pollution Control
6: Construction Site Water Pollution Control
a) Total Construction Cost
Prepare
SW
PPP
Prepare
WP
CP
$0 to $500,000 $2
,200 + RQM $1,000
$500,000 to $1,000,000 $2,700 + RQM $1,100
$1,000,000 to $1,500,000 $2
,800 + RQM $1,100
$1,500,000 to $12,000,000 $3,200 + RQM $1,200
Greater than $12,000,000 $6
,000 + RQM -
Note: Information derived from 2009 average bid costs using Caltrans Cost
D
atabase with an additional mark-up to account for qualified developers of the
SWPPP.
Routine Quarterly Non-Storm Water Monitoring (RL 1, 2, and 3): All projects required to
develop a SWPPP regardless of the RL are to conduct quarterly non-storm water visual
monitoring and storm-triggered visual monitoring. To develop cost estimates for routine,
quarterly, non-storm water monitoring, equation 1 below should be used. The costs for
storm-triggered visual monitoring is assumed to already be included in the costs for
preparing a SWPPP, as this was already a Caltrans requirement prior to the development of
the new CGP.
The cost of routine quarterly monitoring (RQM) for non-storm water discharges is a
f
unction of the project duration, the drainage area, and the cost per inspection, and can be
estimated using Equation 1 as follows:
RQM Cost = (Months/3 + 1) x (N + 4) x Labor (Eqn. 1)
where:
Months = the number of months the project will be occurring, including from
i
nitial site work through the construction until soil is completely
stabilized after construction. This is used to estimate the number of
required quarterly inspections.
N = calculated number of discharge locations. It is assumed that each
d
ischarge area can be reviewed within 1 hour. An additional 4 hours
is provided to account for the time required to complete reporting
and follow-up.
Labor = estimated hourly labor rate for a qualified inspector. Assume $100
p
er hour is appropriate.
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
2
SECTIONFOUR Precipitation and other Climate Data
1.5. RAIN EVENT ACTION PLAN (BEES ITEM: 074056)
All RL2 and RL3 projects are to implement a Rain Event Action Plan (REAP) in advance
of a forecasted storm. The contractor evaluates site readiness as part of formulating a
REAP. This contract item is non-adjustable.
The PE is to set aside $500 for each REAP that is anticipated to be prepared by the
construction contractor. To determine the number of days, use the mean number of days
reported for precipitation producing greater than or equal to 0.1 inches for the duration of
the project. Use climate data from a nearby representative station identified in the Water
Quality Planning Tool or published by the National Climatic Data Center of the National
Oceanic Atmospheric Administration
at:
(http://cdo.ncdc.noaa.gov/climatenormals/clim20/state-pdf/ca.pdf )
.
Another convenient method to find climate data is using District 8s internal website at:
(http://sv08arcgis/cgp2009/). The published National Climatic Data Center information can easily
be located nearest to your project.
Figure 1-1 Find Climate Data Using D8s Internal Website
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
3
SECTIONFOUR Precipitation and other Climate Data
1.6. STORM WATER ANNUAL REPORT (BEES ITEM: 074057)
In order to account for the submittal of an annual report to the RWQCB regarding project
compliance with the CGP, the PE should set aside $2,000 for each year of construction.
This contract item is non-adjustable.
1.7. STORM WATER SAMPLING AND ANALYSIS DAY (BEES ITEM: 074058)
Storm Water Sampling and Analysis (monitoring) costs have become more discernable due
to new requirements of the CGP; consequently, the cost is to be associated with a unit price
in the PS&E. Monitoring costs for compliance with the CGP can be estimated using the
procedures and equations described below. Be sure to use only those procedures
applicable to the RL of the project and the associated representative number of rain days.
This contract item is non-adjustable.
The estimating procedure outlined below accounts for sampling and analysis costs based
primarily on the precipitation characteristics, discharge locations, and construction
duration of the project. The sections below outline the types of sampling and analysis
required for different RL 2 and RL 3 projects and how to develop associated cost
estimates.
Storm Water Monitoring for pH and Turbidity: Sampling and analysis of storm water
runoff for pH and turbidity is required at all RL 2 and RL 3 projects. At a minimum, 3
samples must be collected per day of qualifying storm events, which are those producing
precipitation of 0.5-inch or more at the time of discharge.
The cost of storm water monitoring (SWM) is a function of the precipitation frequency,
construction duration, and the number of sampling locations for the project, as well as the
cost per sample. The SWM cost can be estimated using Equation 2 as follows:
SWM Cost = M x {[Days
0.5”
x $1000] + $2000 (1 + 0.1 (Months/12))} (Eqn. 2)
where:
M = cost multiplier based on the number of anticipated discharge
sampling points. When M = 1, the cost estimate assumes that up to
7 locations can be sampled by one fully equipped staff per event.
Sites with 8 to 14 sampling locations assumes that one additional
staff-day will be required, thus M=2. For sites with 15 – 21
sampling locations M=3, and so forth.
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
4
SECTIONFOUR Precipitation and other Climate Data
Days
0.5”
= estimated total number of days over project timeline with
precipitation event greater than 0.5 inches. However, it is
recommended that the difference between the mean number of days
for both precipitation events greater than 0.5 inches and 0.1 inches
be used. Use climate data from a nearby representative station
identified in the Water Quality Planning Tool or published by the
National Climatic Data Center of the National Oceanic Atmospheric
Administration at:
http://cdo.ncdc.noaa.gov/climatenormals/clim20/state-pdf/ca.pdf
Months = the number of months the project will be occurring, including from
initial site work through the construction until the site is completely
stabilized after construction.
$1000 = daily cost to perform sampling and analysis, as well as reporting,
using one staff at up to 7 discharge locations, excluding equipment.
$2000 = purchase cost for field turbidimeter, pH meter, calibration solutions,
rain gauge, and all ancillary sampling equipment. A maintenance
and calibration estimate of 10% per year is included in the equation.
The cost storm water sampling and analysis per day can be estimated using Equation 3 as
follows:
Storm Water Sampling and Analysis Day = SWM Cost / Days
0.5”
(Eqn. 3)
1.8. RECEIVING WATER BIOASSESSMENT (RL 3) (BEES ITEM:_______)
Bioassessment monitoring in receiving waters is required for all RL 3 projects that have
30 acres or more of disturbed area and directly discharge into receiving waters impaired for
sediment or listed with beneficial uses of COLD and SPAWN and MIGRATORY.
Bioassessment monitoring is required both upstream and downstream of the impacted area,
and both before and after the project. The CGP contains an estimate of $7,500 per sample
for this type of work. To account for this work, a supplemental cost of $30,000 should be
added to all RL 3 projects that disturb 30 or more acres and directly discharge into the
qualifying receiving waters.
1.9. WATER POLLUTION CONTROL MAINTENANCE SHARING (BEES
ITEM: 066595)
The Supplemental Work item for Water Pollution Control Maintenance Sharing still exists
but has been shifted to the individual separate item BMPs that allow for cost sharing.
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
5
SECTIONFOUR Precipitation and other Climate Data
Water Pollution Control Maintenance Sharing cost should be no lower than the amount
es
timated for Prepare SWPPP (or Prepare WPCP). The following may be used to estimate
BMP maintenance costs based upon input from Districts where this approach was piloted.
The aggregate total of estimated maintenance costs would be combined into item WPC
Maintenance Sharing:
a) Temp. Silt Fence, estimate at 10% of the separate item cost per rainy season.
b) Temp. Fiber Roll, estimate at 10% of the separate item cost per rainy season.
c) Temp. Erosion Control and other hydraulically applied soil stabilization BMPs,
estimate at 10% of the separate item cost per rainy season.
d) Temp. Gravel Bag Berm, estimate at 25% of the item cost per rainy season.
e) Temp. Drainage Inlet Protection, estimate at 25% of the item cost per rainy
season.
f) Temp. Construction Entrance, estimate at 25% of the item cost per rainy season.
1.10. ADDITIONAL WATER POLLUTION CONTROL (BEES ITEM: 066596)
The Supplemental Work item for Additional Water Pollution Control will cover additional
WPC BMPs suggested by the RE or Contractor. This change order work is expected to be
minor for most projects. Estimate this item using the same rate as for Prepare SWPPP, less
RQM for SWPPP jobs. For WPCP jobs estimate at the same rate as Prepare WPCP.
1.11. STORMWATER SAMPLING AND ANALYSIS (BEES ITEM: 066597)
The Supplemental Work item for Storm Water Sampling and Analysis covers the cost of
lab tests for water quality samples. Estimate this item using the same rate as for Prepare
SWPPP less RQM.
Sampling and analysis for non-visible pollutants is not often required unless previous site
contamination is present, or WPC practices are failing and result in a discharge. The
number of samples, sampling frequency, and analyses for this type of monitoring is
unpredictable for this reason. It is recommended to account for this work as a supplemental
cost due to previous site contamination in coordination with the Hazardous Waste
Coordinator and District NPDES Storm Water Coordinator.
Sampling and analysis for suspended sediment concentration (SSC) is only required at RL
3 sites with previous exceedances of the daily average turbidity NEL. The additional labor
cost required to conduct this sampling would be minimal since this would occur
concurrently with existing sampling for pH and turbidity, therefore the primary costs
would be analytical and reporting. Analytical costs are typically $100 per sample. Since
the quantity of samples is unknown, as this is a function of an exceedance of the NEL at
the project site, the PE should not assign any supplemental costs for this monitoring.
Receiving water quality monitoring is required only at RL 3 sites where exceedances of the
NEL have occurred and there is a direct discharge to a receiving water. Since it is unknown
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
6
SECTIONFOUR Precipitation and other Climate Data
whether exceedances will occur, this cost can not be predicted nor should it be accounted
fo
r as a supplemental cost.
1.12. ALL OTHER SEPARATE ITEM BMPS
For the variety of separate contract item BMPs the Item Cost database on the OE website
will be sufficient. The items mentioned previously are not tracked so other methods must
be used as tools for guidance. Also refer to PPDG, Table F-5 for individual BMP costs and
Appendix C2 for estimating ATS.
Caltrans Storm Water Quality Handbook
Estimating Guidance for CGP
7